NSW Apartment Design Guide (ADG) Compliance Check
Compliance check for residential flat buildings — every ADG criterion in Parts 3-4 plus the 9 Schedule 9 design quality principles plus the cl 147 Housing SEPP gate.
Apartment developers, registered architects, design teams and certifiers running RFB DAs through any NSW council.
SEPP 65 was repealed — but the ADG continues
On 14 December 2023, the standalone State Environmental Planning Policy 65 — Design Quality of Residential Apartment Development was repealed. Its provisions transferred into Chapter 4 of the State Environmental Planning Policy (Housing) 2021, with the 9 design quality principles renumbered into Schedule 9 of that SEPP. The Apartment Design Guide (ADG) itself continues unchanged as the substantive design standard.
If you're working off old advice or templates, update your cites. SEPP 65 is gone. The current cite is Housing SEPP Chapter 4 + Schedule 9 + the ADG. Our compliance check uses the current cites.
When the ADG applies
The Apartment Design Guide applies to residential flat buildings (RFBs) of 3 or more storeys with 4 or more apartments. It also applies to mixed-use buildings with apartments and adaptive reuse delivering apartments. Cl 147 of the Housing SEPP triggers the assessment: development consent must not be granted to residential apartment development unless the consent authority has considered the design quality of the development against Schedule 9 and the ADG.
The proposal must include a Design Verification Statement signed by a registered architect — mandatory under cl 147(b). The DVS confirms compliance with the 9 design quality principles. Without the DVS, the DA cannot be approved.
The in-fill affordable housing bonus
Under Chapter 2 Part 2 Division 1 of the Housing SEPP, an apartment proposal that includes more than 15% of GFA as in-fill affordable housing apartments gets a 30% uplift to the LEP standards for height of buildings and floor space ratio. So a baseline 20m / 2:1 site becomes 26m / 2.6:1 — significantly more development capacity in exchange for committing some apartments to affordable rental for 15+ years.
Variations to the bonus standards are possible under Section 16(3) of the Housing SEPP — distinct from the standard Cl 4.6 variation mechanism in the LEP. We've audited a real DA where a 1.89% variation to the bonus HOB (26.49m vs 26m) was approved on this basis (Frenchs Forest DA2025/1322, 8-storey 45-apartment RFB).
What the check covers
41 standards — the 9 Schedule 9 design quality principles plus 32 ADG criteria across Parts 3 (Siting the Development) and Part 4 (Designing the Building).
- Schedule 9 design quality principles — Context and neighbourhood character, Built form and scale, Density, Sustainability, Landscape, Amenity, Safety, Housing diversity and social interaction, Aesthetics
- ADG Part 3 Siting — Site Analysis, Orientation, Public Domain Interface, Communal and Public Open Space, Deep Soil Zones, Visual Privacy
- ADG Part 3F — Visual Privacy specifically (separation distances, sill heights, screening)
- ADG Part 4 — Building dimensions (storey heights), Apartment size and layout, Solar and daylight access, Natural ventilation, Ceiling heights, Apartment minimum areas, Balconies and private open space, Common circulation and spaces
- ADG Part 4 continued — Storage, Acoustic privacy, Noise and pollution, Apartment mix, Ground floor apartments, Facilities and waste, Landscape design, Planting on structures, Universal design
- Pathway gates — cl 147 Housing SEPP, Design Verification Statement, Design and Sustainability Advisory Panel referrals
- Bonus mechanisms — in-fill affordable housing 30% uplift (cl 16-21), LMR Stage 2 catchment uplift
- Variations — Cl 4.6 LEP, Section 16(3) Housing SEPP, ADG departure justification
Real fixture: Frenchs Forest 8-storey RFB
DA2025/1322 at 106 Frenchs Forest Road West (Northern Beaches Council, R3 zone). 8-storey, 45-apartment residential flat building including in-fill affordable housing under Housing SEPP. Cost $23.26M. NBLPP-determined 15/04/2026. Base WLEP 2011 standards 20m HOB and 2:1 FSR; 30% in-fill affordable housing bonus uplifted to 26m and 2.6:1. Approved with a 1.89% variation to the bonus HOB (26.49m vs 26m) under Section 16(3) of the Housing SEPP (different mechanism to standard Cl 4.6). The NBLPP Assessment Report runs 123 pages with a clause-by-clause ADG compliance table starting around page 46 — that's the structure our compliance check mirrors.
The statutory framework
NSW apartment design quality is regulated under multiple instruments, all referencing the ADG.
Housing SEPP 2021 Chapter 4
Apartment design quality. cl 147 — gate clause: consent must not be granted unless the consent authority has considered design quality against Schedule 9 and the ADG. cl 147(b) — Design Verification Statement requirement
Housing SEPP 2021 Schedule 9
9 Design Quality Principles — Context and neighbourhood character, Built form and scale, Density, Sustainability, Landscape, Amenity, Safety, Housing diversity and social interaction, Aesthetics
Apartment Design Guide (DPHI)
Substantive design standard. Part 3 Siting the Development, Part 4 Designing the Building. Numerical criteria (apartment minimum areas, ceiling heights, solar access, natural ventilation) plus qualitative criteria
Housing SEPP 2021 Chapter 2 Part 2 Division 1 (in-fill affordable housing)
30% uplift to LEP HOB and FSR where in-fill affordable housing component exceeds 15% of GFA. Section 16(3) variation mechanism
Note: SEPP 65 was repealed 14 December 2023
Old citations to 'SEPP 65' are out of date. Current cite is Housing SEPP Ch 4 + Schedule 9 + the ADG
Housing SEPP cl 166-180 (LMR Stages 1 and 2)
For RFBs in LMR Stage 2 catchments — uplifted controls within 800m of nominated centres
Frequently asked questions
Is SEPP 65 still in force?
When does the ADG apply?
What's a Design Verification Statement?
What's the in-fill affordable housing bonus?
What about LMR Stage 2 for apartments?
What's the typical document set?
What's a Design and Sustainability Advisory Panel (DSAP)?
Can I get a Cl 4.6 variation on the FSR or HOB?
Related NSW resources
$99 — ready when you are